The goal of NKU is to create a new neighborhood and significant regional facilities. If successful, it will serve families in the North Kitsap community for generations to come. Regional-scale development is an incredibly complex undertaking and involves the coordination of numerous elements including land use, demand analysis, design, fundraising, financing, appeals, and other legal considerations.

The feasibility process itself does not involve public agency review and is being performed to test whether the concept itself is viable, assuming all the land use processes are successful. The land use process diagrams the steps from comprehensive plan application through project construction.

Please note, both processes have been simplified and do not include all steps involved. Timelines subject to change as project concept progresses.

Feasibility Process

July 2023
Community meeting for Q&A
June 2024
Preliminary site plans and business plan
June 2023
Share idea at community meeting
December 2023
Preliminary environmental studies
October 2024
Decision
June 2023
Share idea at community meeting
July 2023
Community meeting for Q&A
December 2023
Preliminary environmental studies
June 2024
Preliminary site plans and business plan
October 2024
Decision

Land Use Process

March 2025
County decision on comprehensive plan amendment (plus appeal period)
December 2027
NKU project approval by County
April 2028
Bidding and construction begins
July 2022
County accepts applications for comprehensive plan amendments
April 2025
Specific NKU project application and SEPA review by County
December 2027
Preparation, review, and approval of construction documents by County
December 2029
Construction complete
July 2022
County accepts applications for comprehensive plan amendments
March 2025
County decision on comprehensive plan amendment (plus appeal period)
April 2025
Specific NKU project application and SEPA review by County
December 2027
NKU project approval by County
December 2027
Preparation, review, and approval of construction documents by County
April 2028
Bidding and construction begins
December 2029
Construction complete
X

This website stores cookies on your computer. These cookies are used to collect information about how you interact with our website and allow us to remember you. We use this information in order to improve and customize your browsing experience and for analytics and metrics about our visitors both on this website and other media. To find out more about the cookies we use, see our Privacy Policy.